Finance/Crystal ball
Answer/complete both of the following two questions. Submit your work products through the appropriate assignments folder by the close of the session. Ensure each file you post includes your last name in the file name.
Question 1: Your firm designs training materials for computer training classes, and you have just received a request to bid on a contract to produce a complete set of training manuals for an 8-session class. From previous experience, you know that your firm follows a 90% learning rate. For this contract, it appears that the effort will be substantial, running 400 hours for the first session. Your firm has an average cost of labor of $60/hour and the overhead is expected to run a fixed $1000 per session. The customer will pay you a flat fixed rate per session (Per Session Price.) If your profit markup is 12%, what will be the Total Price, the Per Session Price, and at what session will you break even?
Answer the following four questions:
- What is the Total Price? This is what you would charge the customer so that you can have your profit markup of 10% over all of your costs. To calculate this, first figure out your cost per each session, add them up, and then add your profit.
- What is the Per Session Price? This is the revenue that the customer pays you each time you complete a session. It is calculated by dividing the Total Price by the number of sessions.
- What is the Break Even Point? At the beginning, your cost per session is more than your revenue per session. As each session is completed, however, your costs for the session declines so that eventually your cumulative revenue exceeds the cumulative cost. The break-even point is the session at which, for the first time, your revenue exceeds your cost.
- Assume you win the contract and your customer likes the training so much, she orders a ninth course at the same price as the first eight. What will your profit be on the 9th course?
- If your learning rate was 80%, would your time to produce a second course be more or less than it was at 90%
Question 2: You have just been assigned as Project Manager (PM) to the Kuraiz-Reconda Fiber Optic Cable (KRFOC) project. You are preparing your cost estimate for the project and your Project Engineer (PE) tells you it will take 425 hours to complete the design effort. Your Finance Manager (FM) tells you that engineering labor is $125 an hour. Fortunately for you, unfortunately for them, you are a graduate, specializing in project management in general and advanced project management techniques in particular.
Upon questioning, your PE admits that the 425 hours is just a guess, that under the best circumstances, meaning you quit bugging him with inane questions, it may take only 375 hours. However, it could take as long as 700 hours (if you do not leave him alone to do his job). He stands by his estimate that it will normally take 425 hours. Hint: this is a triangular distribution.
Thinking back to your school days, you wonder if all engineers cost $125 per hour. Upon questioning, your FM admits that this is an average cost, that the highest salary is $150, the lowest is $100. You direct him to give you the distribution of all engineer labor rates. With a lot of help (your FM does not have the benefit of your school education), he replies that the labor rate is uniformly distributed.
Please answer the following two questions:
- Using this information and a wonderful tool you mastered in school, Crystal Ball (CB), what is the mean cost of your engineering effort?
- You are about to present your cost estimate to your sponsor when you remember that he was once a Professor the same school. You recall, too, that he wore both a belt and suspenders and you suspect that this meant he might be a bit conservative. You therefore decide to provide an engineering cost estimate such that you are confident that 95% of the time your actual costs would be less than that value and that no more than 5% of the time would you exceed that value. What is your new estimate of engineering costs?
- You present your cost estimate to your sponsor. He rejects it as way, way too high. He asks what you intend to do about it. Do you:
1) Fire your engineer.
2) Write your Professor and ask him where you went wrong (after all, you got a D+ in his course).
3) Request the sponsor give you another probability that he is comfortable with and re-run the estimate of costs.
Be sure to provide the results of your CB simulation.
We've got everything to become your favourite writing service
Money back guarantee
Your money is safe. Even if we fail to satisfy your expectations, you can always request a refund and get your money back.
Confidentiality
We don’t share your private information with anyone. What happens on our website stays on our website.
Our service is legit
We provide you with a sample paper on the topic you need, and this kind of academic assistance is perfectly legitimate.
Get a plagiarism-free paper
We check every paper with our plagiarism-detection software, so you get a unique paper written for your particular purposes.
We can help with urgent tasks
Need a paper tomorrow? We can write it even while you’re sleeping. Place an order now and get your paper in 8 hours.
Pay a fair price
Our prices depend on urgency. If you want a cheap essay, place your order in advance. Our prices start from $11 per page.