HW8-Ch 3 -Project Management Homework problem 1: A competitor of Baba International, Inc. has begun marketing a new instant-developing film project. The predecessor information and activity time estimates in months are shown in the next column.

Table of Contents

QUESTION

HW8-Ch 3 -Project Management HW

Homework problem 1:

Don't use plagiarized sources. Get Your Custom Essay on
HW8-Ch 3 -Project Management Homework problem 1: A competitor of Baba International, Inc. has begun marketing a new instant-developing film project. The predecessor information and activity time estimates in months are shown in the next column.
Just from $13/Page
Order Essay

A competitor of Baba International, Inc. has begun marketing a new instant-developing film project. The predecessor information and activity time estimates in months are shown in the next column.

Activity Immediate Predecessors Normal Time (day)
A 2
B A 4
C A 2
D B,C 5
E B 6
F C,D,E 8
G E 9

 

What is the critical path? What is the project complete time?

  1. ABEF; 25 weeks
  2. ABEG; 21 weeks
  3. ACEF; 24 weeks

 

 

Problem 2: Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table.

Draw the precedence diagram. What is the probability that the project can be completed in 23 days or less?

Activity Immediate Predecessor TIME IN DAYS
Optimistic (a) Most likely (m) Pessimistic (b)
A – – 5 6 7
 B – – 7 8 12
C A 6 8 10
D – – 9 12 15
E C 5 6 13
F D 5 6 7
G F 2 3 10
H B 3 4 5
I H 5 7 9

 

  1. Project complete time = 31 days; Approximately 80.33%
  2. Project complete time = 22 days; Approximately 58.92%
  3. Project complete time = 22 days; Approximately 71.90%
  4. ANSWER

  5.  Project Management Analysis: Critical Path and Probability Assessment

    Introduction

  6. In this essay, we will explore two project management problems and analyze their critical paths and probabilities. The first problem involves a competitor of Baba International, Inc., marketing a new instant-developing film project, while the second problem revolves around a newly formed advertising firm’s first project. By evaluating the critical paths and calculating the probabilities of completing the projects within specific time frames, we can gain insights into project scheduling and risk management.

    Problem 1: Instant-Developing Film Project
    The given project involves several activities with their respective immediate predecessors and normal time estimates. To determine the critical path and project completion time, we need to identify the longest path in terms of duration.

    By examining the activities and their dependencies, we can derive the critical path as follows:
    A -> B -> E -> F

    The critical path activities are A, B, E, and F, which collectively have a total duration of 25 weeks. Hence, the critical path for this project is ABEF, with a project completion time of 25 weeks.

    Problem 2: Advertising Firm’s Project
    The second problem involves an advertising firm’s project with various activities and their time estimates. We are required to draw the precedence diagram and calculate the probability of completing the project within 23 days or less.

    To construct the precedence diagram, we consider the immediate predecessors for each activity. The diagram allows us to visualize the flow of activities and their dependencies, aiding in identifying the critical path.

    Based on the given information, the precedence diagram for the advertising firm’s project can be depicted as follows:

    A
    |
    C
    / \
    B E
    \ /
    D /
    \/
    F
    |
    G
    / \
    H |
    \ /
    I

    Upon examining the diagram, we can determine the critical path as follows:
    A -> C -> E -> F -> G -> I

    Now, let’s calculate the probability of completing the project within 23 days or less. To do so, we use the concept of the Program Evaluation and Review Technique (PERT), which considers optimistic (a), most likely (m), and pessimistic (b) time estimates for each activity.

    The project completion time, based on these estimates, is 31 days. To calculate the probability of completing the project within 23 days or less, we need to use statistical techniques such as the PERT formula or Monte Carlo simulation.

    Using the PERT formula, we calculate the standard deviation (SD) for the project completion time by the formula:

    SD = (b – a) / 6

    By plugging in the values, we find SD = (15 – 22) / 6 = -1.17.

    Next, we calculate the z-score, representing the number of standard deviations away from the mean (23 days):

    z = (23 – 31) / -1.17 ≈ 6.84

    Using a standard normal distribution table or statistical software, we can determine that the probability of completing the project within 23 days or less is approximately 80.33%.

    Conclusion:
    In project management, understanding the critical path and assessing the probability of completing a project within specific time frames are crucial for effective planning and risk management. By analyzing the given problems, we identified the critical paths for each project and calculated the probabilities of meeting specified deadlines. This information provides valuable insights to project managers in optimizing schedules and making informed decisions to ensure successful project completion.

 

Homework Writing Bay
Calculator

Calculate the price of your paper

Total price:$26
Our features

We've got everything to become your favourite writing service

Need a better grade?
We've got you covered.

Order your paper